N. Putnam Project Update

Posted on April 15, 2024


North Putnam Update

Work will begin on April 15, and continue through May 31, with restoration work happening in June.  North Putnam will be closed to through traffic.

  • One lane will be open during construction for residents to access the homes and for construction activity.
  • The contractor will work on west side and east side as separate phases, including sidewalk. One side will be completed (aggregate base, curb, sidewalk) before moving to the other side.  Paving will be one operation at the end of the project.
  • Milling the asphalt will be the first operation. Millings will be left in place as temporary driving surface until aggregate base placement occurs.
  • Paving limits extend from West Riverside to Bismark.